Timeline for New Science Building

January 2017 – March 2018  -  
Design Phase
March 2018 Ground Breaking Ceremony
August 2021 Phase I Construction Completed
August 2021     
Phase II Demolition of NSB Starts
December 2021            
Phase II Construction Completed
January 2022                     
Project Completion

 

 

 